The entire house generator quote was effectively communicated through multiple emails and phone conversations. The sales person was well versed in the selection and electrical aspect of the needed work.
Following the contract signing, Alternative Power secured city permits and scheduled the installation date. The physical and electrical installation process was completed within six hours, with preliminary electrical approvals obtained from the city inspector. The gas connection was finalized the following day.
The start-up was scheduled for after four days of final electrical and gas inspections. The total time for the start-up process was three hours, including and excluding load. I requested the start-up checklist, which should have been provided at the conclusion of the start-up but was delayed for several days.
A minor issue was the uncleaned electrical panels, which I vacuumed during the start-up process. It is essential that electrical panels are free from debris. Additionally, the dirt from the electrical conduit ditch was left on top of the nearby condensate drip collection point, which Alternative Power removed the following day.